Historical Data Working Group 07 Work Plan
FY 2007
Agency Name: NARA/LOC/USGS/FSA/CIESIN/NCState
Subcommittee or Working Group: Historical Data Committee
Background: Held two sessions at ESRI Federal Users Conference in February determining the viability of archiving GIS data. Determined the current state and probable steps needed to be incorporated into an archival profile. Began process of involving OGC in the development of an archival profile for GIS data.
Objectives: Begin process of developing an archival profile for GIS data, using GML and Simple Features profile.
Benefits or Justification/Legal Mandate: Establishes nonproprietary format for preserving GIS data over the long term.
Scope of Work: Identify willing participants from HDWG to work with members of OGC.
Milestones, Schedule, and Budget
| Action | Date | Who? | Others? | Budget |
|---|---|---|---|---|
| Coordinate with Representatives from the OGC toward developing Archival Profile for GIS | By October 31 | David Arctur, OGC Interoperability Institute HDWG/NARA | Members of the OGC TC—meeting at conference in Tyson Corner Oct. 4th | ? |
| Identify people to develop profile | By December 31 | HDWG/OGC | FGDC OGC Representative | |
| Monitor development process | By March 31 | OGC/HDWG |
Subcommittee or Working Group: Historical Data Committee
Background: The two federal agencies joined the Geospatial One Stop (GOS) as data stewards for the Historical Collections community.
Objectives: Develop a presence on Geospatial One Stop portal.
Benefits or Justification/Legal Mandate: Meets NARA and LOC negotiated understanding with the Office of Management and Budget for the fiscal year.
Scope of Work: Develop necessary technical and content expertise within agencies. Create language identifying community for introduction pages and add material to site under the community.
Milestones, Schedule, and Budget
| Action | Date | Who? | Others? | Budget |
|---|---|---|---|---|
| Coordinate with needed staff for support | By October 1 | NARA | ||
| Upload material for community | By October 31 | NARA | ||
| Monitor development process | By March 31 | NARA | ||
| Monitor usage of site | ongoing |
Identification of funding sources or requests
Points of Contact, Contact Info, and Area of Responsibility
Brett Abrams, NARA/Colleen Cahill, LOC